EDUCATIONAL AND CHARITABLE TRUST Registered No: 454/2004
web: www.indiasudar.org email: admin@indiasudar.org Flat No. D, No. 2/43 2nd
Street Vedha Nagar, Chinmaya
Nagar Stage II Ext, Chennai - 600 092 |
|||||||||||||||||
PROJECT REPORT |
|||||||||||||||||
Project Code |
1 |
Project Name |
STAFF |
Category |
NT Project Staff |
||||||||||||
Work Code |
1.806 |
Financial Year |
2022-23 |
State |
TN |
||||||||||||
Work Description |
India Sudar
deployed the Liaison Manager (Part Time) for the GHSS Pallikaranai
school in the ÒLHPÓ project. |
||||||||||||||||
Fund Owner(s) |
Code |
Name |
Amount |
||||||||||||||
P41 |
Ford Motors Pvt Limited |
27,000 |
|||||||||||||||
Work Coordinator(s) |
Code |
Name |
|||||||||||||||
|
Balamanikandan
K |
||||||||||||||||
Onsite/Student Code |
Onsite / Student Name |
Onsite / Student Address |
|||||||||||||||
OTN00 |
Govt. Hr.Sec.School |
Pallikaranai, Chennai-600 100 |
|||||||||||||||
No of Beneficiary |
Onsite Contact Details |
Onsite About |
|||||||||||||||
556 |
Udhayakumar V Mob : 98402 95650 |
School
is selected from Chennai based on site visit and
assessment. Students are from financially disadvantaged backgrounds. |
|||||||||||||||
Target Classes |
NA |
||||||||||||||||
Project Start Date |
01-July-2022 |
Project
End Date |
31-Mar-2023 |
Nof Months for Staff / Nof hrs for Training |
9 months |
||||||||||||
Staff Details (Only for STAFF) |
Code |
Name |
Qualification |
Salary Per Month |
|||||||||||||
NA |
SUBAPRIYA K |
M.Sc., M.Phil., M.Ed., D.Y.Ed., |
3,000 |
||||||||||||||
Course Details (Only SCHOLARSHIP) |
Course Name |
Institute Address |
|||||||||||||||
NA |
NA |
||||||||||||||||
Library Details (Only for LIBRARY) |
No. of Books/Magazines |
||||||||||||||||
NA |
|||||||||||||||||
S.NO |
Expense Details / Purpose |
Amount Spent (INR) |
|||||||||||||||
1 |
9 MonthÕs Salary (9 x
3000) |
27,000.00 |
|||||||||||||||
Total Work Cost. INR |
27,000.00 |
||||||||||||||||
Transaction from India Sudar ICICI
Bank. A/C: 000901112899 (Domestic in INR) |
|||||||||||||||||
CHQ EFT PFR |
Payee Name |
Date (DD-MON-YYYY) |
Amount (INR) |
Cheque No |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Aug-2022 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Sep-2022 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Oct-2022 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Nov-2022 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Dec-2022 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Jan-2023 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Feb-2023 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
05-Mar-2023 |
3000 |
NA |
|||||||||||||
EFT |
K. SUBAPRIYA |
31-Mar-2023 |
3000 |
NA |
|||||||||||||
Declaration (Not applicable for
Scholarship) |
1. India Sudar is the
owner for the movable assets provided. India Sudar
has 100% Power to take back all the movable assets provided by India Sudar at any time based on the usage and maintenance.
The beneficiary does not have any privilege to sell or move the movable
assets to anywhere. 2. The staff deployed by India Sudar should be assigned the specific purpose mentioned
in this report. They should not be overburdened by additional
responsibility. |
||||||||||||||||
Accepted by INDIA
SUDAR, The President/Managing
Trustee/Trustee |
Accepted
by Beneficiary |
||||||||||||||||
(BALAMANIKANDAN K) |
(SUBAPRIYA K) |
||||||||||||||||