PROJECT REPORT

Project Name

Providing computer infrastructure

Work Code

5.28/TN/2018_2019

Coordinator

Ram Kumar P

On Site

OTN100- Govt. High School, Mettukuppam, Kurinjipadi Block, Cuddalore Dt- 607802

On Site Contact

Head Master

Work Description

Release 1:

India Sudar has provided EPSON EB - S41 SVGA PROJECTOR and screen with HDMI to VGA adapter and cables to GHS Mettukuppam  to facilitate audio visual class room. The same infrastructure will also

help the school in conducting seminars, awareness sessions etc.

Release 2:

Customised wooden extension box with long cable is prepared and provided in order to conduct seminars and functions

Release 3:

Moved the 2 CPUs (used ones) from ford motor pvt limited, Chennai to the school.

Work Duration

All the Working Days

Working Hours

9 am to 4 pm daily

Beneficiary

Approx. 257 students (every year)

India Sudar

Power and Responsibility

  • India Sudar is the owner for the items provided. India Sudar has 100% Power to take back all the infrastructure provided at any time based on the usage and maintenance of the infrastructure.

School Responsibility:

  • School should take care of the maintenance activity.
  • School does not have any privilege to sell or move the properties.

Project Cost

#

BILL OF MATERIAL

COST

1

EPSON EB - S41 SVGA PROJECTOR - 1 nos

26200

2

Projector Screen

4250

3

10 meter cable and one adapter

1400

4

Material cost, Gaadi charges,Labour Charges

1493

5

Vehicle  charges (Vadalur -Chennei to Vadalore 430  kms) and Toll fee

1596

 

TOTAL COST in INR

34,939

Payment mode

Online from Indiasudar ICICI Bank.A/C: 000901112899 (Domestic)

Transaction Information

Online :

Release1 :

Pay To : Apple systems

Pay Date : 15-Sep-2018,22-Sep-2018

Amount : Rs. 26,200 and Rs.5,650

No of Transfer : 2

Release 2 :

Pay To : Tamizhan

Pay Date : 25-Oct-2018

Amount : Rs. 1493

No of Transfer : 1

Release 3:

Pay To : Ramkumar. P

Pay Date : 15.12.2018

Amount : Rs. 1596

No of Transfer : 1

Completed Date

13.12.2018

Total Cost /expenditure in INR

Rs. 34,939

Work Status

COMPLETED

Accepted By 

INDIA SUDAR (Managing Trustee)

Accepted By

The Headmaster

 

 

 

 

 

(BALAMANIKANDAN K)

 

 

 

 

 

(Head Master’s Signature with Name and seal)